Report an issue

Report an issue on a Larimer County maintained road, bridge or drainage structure. 

This email address is not monitored after hours. For emergency issues after hours or on weekends, please contact Larimer County Sheriff's Dispatch at (970) 416-1985 or dial 911.



Highlights

CR 80C Re-Graveling Project

SCOPE OF WORK

Project limits are from the top of Calloway Hill west ~ 4 miles to just west of the Livermore Fire Protection District Station.  The goal of the project is to re-establish proper roadside drainage, establish a 28’ wide roadway platform and surface the road with 6” of aggregate base course.  This segment of road gets slick and soft during moisture events and has steadily worsened over the years.

PROJECT STATUS

Work began December 1, 2021 and is scheduled to be complete in the fall of 2022.  Construction will be suspended during the summer of 2022 so crews can complete other scheduled work

CONTACT:

Jerry Macklberg, Group Manager
(970) 498-5670
Email Jerry Macklberg

 

Big Elk Meadows Road (CR 47) to be Reconstructed

Project No. 9332

(CR 47 Permanent Roadway Flood Repairs)

 

SCOPE OF WORK

The remaining work consists of rebuilding and paving 2 miles of CR 47 including three crossings of the West Fork of the Little Thompson River in lieu of damages caused during September 2013 flooding.  The goal is to re-pave these damaged portions of roadway, asphalt patch and overlay the remaining paved sections within the two miles of flood damage, construct the road back to the pre-flood elevation, and make the creek crossings more resilient during future high flow events while passing a 25-year storm event.  An asphalt patching and overlay project will also be completed using Larimer County funds for the remainder of the paved portion of CR 47 to the Johnny Park Fork.

Reconstruction/realignment work on County Road 47 from Highway 36 south approximately 900' occurred in 2015.  This portion was managed through a contract with the Federal Highway Administration, Central Federal Lands Highway Division (CFL). Traffic was diverted over the new bridge during the summer of 2015.  Larimer County contracted the paving of the first 900’ and guardrail placement at the new bridge.  This work is complete.

PROJECT STATUS

Larimer County has finalized and submitted environmental evaluations to the appropriate state and federal agencies in 2021.  The environmental reviews and approval processes are complete.

The project was advertised for bids on July 15th, 2021. The construction contract has been awarded to Dietzler Construction.  Construction on the three stream crossings has begun with traffic being diverted through a one-lane temporary traffic signalized operation.Paving will occur in mid-2022.

Project Budget: Larimer County is seeking federal (FEMA – 75%) and state (-DHSEM and a HUD Community Block Grant – each 12.5%) reimbursement for the proposed repairs. The construction cost estimate is $6,800,000.

CONTACT:

Matt Johnson, Project Manager
(970) 498-5724
Email Matt Johnson

 

Estes Park Facility
543 Elm Road
Estes Park, CO 80517

Laramie River Facility
21137 CR #103
Glendevey, CO
(mail: Jelm, WY 82063)

Livermore Facility
124 West CR 74E
Livermore, CO 80545

Loveland Facility
2205 East SH #402
Loveland, CO 80537

Stove Prairie Facility
17290 Rist Canyon Rd
Bellvue, CO 80512

Waverly Facility
241 W. CR #70
Waverly, CO 80549

FAST FACTS

ROADS

  • 382 Miles of  paved roads (48%)
  • 419 Miles of non-paved roads (52%)
  • 100 Miles of Subdivision Roads

Average Vehicle Miles Traveled on Larimer County Roads

  • Paved Roads = 325 Million VMT (91%)
  • Non-paved Roads = 31 Million VMT (9%)

SNOW & ICE CONTROL

  • 684 Mainline miles plowed
  • 88 Subdivisions = 84 miles plowed
  • 5,832 tons of ice & traction control material utilized
  • Average number of man hour per year on snow events = 12,967 hours

STRUCTURES & SIGNS

  • 213 Major structures (>20 ft.)
  • 449 Minor structures (<20 ft.)
  • 4,300+ Cross culverts
  • 10,657 Sign mounts w/ 13,189 sign panels
  • Road & Bridge Mill Levy (2020) = .813
  • $24.70 = The annual amount collected on property taxes that is for road maintenance purposes. Based on a residential structure valued at $425,000.

 

 

Road Maintenance Costs Per Mile

  • Paved Roads - $16,240
  • Non-Paved Roads - $12,980

 

 


CDOT

Weld County


  • Image 1: Road and Bridge Department
county road

CONNECT WITH US

ROAD & BRIDGE DEPARTMENT
ADDRESS: 2643 Midpoint, Suite C, Fort Collins, CO 80525
HOURS: Monday-Friday, 7:00am-4:30pm
PHONE: (970) 498-5650
EMAIL: rab-admin@co.larimer.co.us

"Per the Americans with Disabilities Act (ADA), Larimer County will provide a reasonable accommodation to qualified individuals with a disability who need assistance. Services can be arranged with at least seven business days' notice. Please email us at rab-admin@co.larimer.co.us or by calling (970) 498-5650 or Relay Colorado 711. "Walk-in" requests for auxiliary aids and services will be honored to the extent reasonable but may be unavailable if advance notice is not provided."

Facebook Twitter