Report an issue

Report an issue on a Larimer County maintained road, bridge or drainage structure. This email address is not monitored after hours. For emergency issues after hours or on weekends, please contact Larimer County Sheriff's Dispatch at (970) 416-1985 or dial 911.

 

Annual Maintenance Activity Calendar

Highlights

County Road 44H Reconstruction

The County was on track to advertise the project for bids this spring after a full Environmental Assessment but FEMA just recently defunded the greater reconstruction project and will fund only improvements to bring the road back to pre-flood conditions plus some undetermined mitigation work. Revised plans will be presented to FEMA in May for review.  It’s unknown when construction may begin.


County Road 80C Resurfacing Project

SCOPE OF WORK

The Road and Bridge Department is working on a project to surface a nine-mile section of County Road 80C between Cherokee Meadows Road and County Road 59.  This section of road is currently a native surface and will receive a six-inch layer of aggregate base course.  The project will include improvements to the roadside drainage, replacement of several drainage culverts, minor width and horizontal alignment improvements and the import and placement of ~45,000 tons of aggregate base course. 

SCHEDULE

Road and Bridge crews began work on the project in December of 2017. After being suspended to make way for summer projects, work on this project has resumed for the fall and is currently expected to be completed in Spring of 2019.

Estes Park Facility
543 Elm Road
Estes Park, CO 80517

Laramie River Facility
21137 CR #103
Glendevey, CO
(mail: Jelm, WY 82063)

Livermore Facility
124 West CR 74E
Livermore, CO 80545

Loveland Facility
2205 East SH #402
Loveland, CO 80537

Stove Prairie Facility
17218 CR #52
Bellvue, CO 80512

Waverly Facility
241 W. CR #70
Waverly, CO 80549

FAST FACTS

ROADS

  • 384 Miles of  paved roads (48%)
  • 419 Miles of non-paved roads (52%)
  • 101 Miles of Subdivision Roads

Average Vehicle Miles Traveled on Larimer County Roads

  • Paved Roads = 314.9 Million VMT (91%)
  • Non-paved Roads = 29.6 Million VMT (9%)

SNOW & ICE CONTROL

  • 686 Mainline miles plowed
  • 89 Subdivisions = 86 miles plowed
  • 4,967 tons of ice & traction control material utilized
  • Average number of man hour per year on snow events = 9,513 hours

STRUCTURES & SIGNS

  • 217 Major structures (>20 ft.)
  • 481 Minor structures (<20 ft.)
  • 4,000+ Cross culverts
  • 10,390 Sign mounts w/ 11,964 sign panels
  • Road & Bridge Mill Levy (2019) = .937
  • $24.00 = Road & Bridge portion of property tax on a residential structure valued at $350,000 (with only $14.88 retained by Larimer County).


Weld County


  • Image 1: Road and Bridge Department
Paved road

CONNECT WITH US - ROAD & BRIDGE DEPARTMENT

ADDRESS: 2643 Midpoint, Suite C, Fort Collins, CO 80525
HOURS: Monday-Friday, 7:00am-4:30pm
PHONE: (970) 498-5650
EMAIL: rab-admin@co.larimer.co.us |  Seasonal Employee Login

Facebook Twitter