Red Feather Lakes Road Drainage Improvements

Project No. 294

(CR 74E Culvert Replacements)

Last Updated:  September, 2018
 

 

SCOPE OF WORK

Replace four culverts in poor condition on CR 74E:

  •  36” and 48” corrugated steel pipes at Parvin Lake
  •  48” steel and concrete pipe at the east approach to McNey Hill
  • 10’ X 8’ concrete box culvert just east of the Lonepine Trailhead (at the curves with guardrail)  

Project Budget:  $2,000,000

PROJECT STATUS

Final plans are almost complete.  The culverts at Parvin Lake will be replaced spring of 2019.  The other two will be replaced fall of 2019.

CONTACT

Joe Temple, Project Manager
(970) 498-5717
Email Joe Temple

 

Old Highway 287 and North Taft Hill Road Intersection Improvements in Design

Project No. 303

(CR 54G / CR 19 Intersection, North of Fort Collins)

Improvements Currently On Hold

Last Updated:  September, 2018

 

SCOPE OF WORK

Improvements to the intersection of CR 54G (old Hwy 287) and CR 19 (N. Taft Hill Road).  The improvements will include construction of a modern roundabout at the intersection.

Project Budget:  $1,000,000

PROJECT STATUS

Preliminary engineering analysis to determine the scope and preferable type of intersection is complete and use of a modern roundabout has been determined to be the appropriate type of intersection improvement. 

Final Design & Construction of improvements is on hold pending funding.

CONTACT

Rusty McDaniel, Assistant County Engineer
(970) 498-5730
Email Rusty McDaniel

Center Turn Lane to be Added to County Road 17

Project No. 317

(Widening of CR 17 from US 287 to CR 16)

Last Updated: September, 2018
 

 

SCOPE OF WORK

Widen County Road 17 (Taft Avenue – Loveland) from US Highway 287 to County Road 16 (2.0 miles) to accommodate a two-way center turn lane and six foot wide shoulders.

Project Budget:  $5,000,000 ($2,865,855 federal grant, $1,534,145 county match, $600,000 Berthoud match)

PROJECT STATUS

Final roadway plans are complete but the design of a storm sewer crossing of Highway 287 added to the project is just underway.   City of Loveland water line relocation at the Home Supply Ditch is complete – coordinating with other utilities on relocation.  Environmental clearance and the addition of the storm sewer (Crestridge Drive to south of US 287) have pushed construction to 2019.

CONTACT

Joe Temple, Project Manager
(970) 498-5717
Email Joe Temple>

Namaqua Road (CR 19E) Bridge Replacement

Project No. 318

(Replacement of Bridge No. LR19E-0.5-20 over the Big Thompson River)

Last Updated: September, 2018

 

SCOPE OF WORK

The project includes the replacement of this deteriorating concrete bridge on County Road 19E (Namaqua Ave.) over the Big Thompson River on the west side of Loveland.  Approximately 500 feet of roadway north and south of the bridge (1000 feet total) will be reconstructed with the project.  Interwest Consulting Group was selected as the design consultant.    Construction is currently scheduled for December 2018 through May of 2019.  The design of the project is funded through a Federal Highway Administration bridge grant.  The construction is funded through a Housing and Urban Development Colorado development block grant for disaster relief.

Project Budget:  $3,700,000

PROJECT STATUS

The preliminary design is complete.  Final design is underway.

CONTACT

Morgan Fay, Project Manager
(970) 498-5739
Email Morgan Fay

CR 70 Reconstruction and Widening In Design

Project No. 322

(CR 70 Owl Canyon between CR 19 and CR 15)

Last Updated: September, 2018

 

SCOPE OF WORK

The project includes 2 miles of roadway widening and reconstruction of CR 70 from the roundabout at CR 19 to the intersection of CR 15.  The two lane roadway will accommodate 6 to 8 feet wide paved shoulders.  Two road crossings of the North Poudre Irrigation Ditch are planned for replacement with new pre-cast concrete box culverts within this corridor.  The first being located directly north of CR 70 on CR 17 and the second between CR 17 and CR 15.  Intersection improvements at CR 15 are not proposed with this phase.

PROJECT STATUS

Topographic surveying of CR 70 between CR 19 and 15 is complete.  Larimer County has hired an engineering consulting firm, Interwest, to design and prepare construction plans.  Existing buried utilities have been field located and surveyed.  The Northern Colorado Water Association bored their new crossings under the North Poudre Irrigation Canal in April 2018.  Environmental investigation and clearances are complete.  Final design is nearing completion.  Staff has been meeting with adjacent landowners regarding right-of-way acquisitions.

Construction is pending utility relocations and right-of-way acquisitions and is anticipated to begin in late 2018.  The buried gas main has been relocated at the east end of the project near CR 15.  Various other utility relocations (phone, overhead electric power, and 2 water mains) are expected to occur during the fall of 2018.

The preliminary design was presented at an open house held on February 22, 2018, at the Eyestone Elementary School Gymnasium in Wellington.  .  Another open house was held on August 29, 2018, at the Leeper Center in Wellington to present the planned two mile construction closure of CR 70 and detour route along CR 72 between CR 19 and CR 15.

Project Budget: $5,950,000.  The project will be funded entirely by Larimer County.

Project Schedule: Begin construction in late 2018 and ongoing through Summer 2018.

CONTACT

Matt Johnson, Project Manager
(970) 498-5724
Email Matt Johnson

County Road 11C / CR 28 Roundabout Construction  

Project No. 324

CR 11C (Boise Ave) / CR  28 ( 57th Street) Intersection

Last Updated: September, 2018
 

 

SCOPE OF WORK

Project includes construction of a roundabout at the intersection to improve safety and capacity.

Project Budget:  $ 1,200,000

PROJECT STATUS

Bids were opened August 22nd and Coulson Excavating was the low bidder.  Construction will begin in late September or early October and be substantially complete in December. Utility relocations have begun and will continue through the beginning of construction. 

We do not anticipate closing the intersection during construction except for a five day closure that we anticipate occurring in October to tie into the existing road.  A detour will be built around the intersection.

CONTACT

Rusty McDaniel, Project Manager
970) 498-5730
Email Rusty McDaniel

LONGVIEW TRAIL TO PARALLEL SHIELDS/TAFT BETWEEN CITIES

Project No. 5030

(Longview Trail)

Last Updated: September, 2018

 

SCOPE OF WORK

Construct a concrete trail with detached soft path between CR 17 (Shields - FC / Taft - Loveland) and the railroad tracks from Fort Collins to Loveland.  Both cities have concurrent projects that will extend the trail to north Fromme Prairie and south to 57th Street (4.4 miles total).

Project Budget:  County Segment - $460,000, total with Cities - $4,000,000

(GOCO Pathways to Parks and CDOT Transportation Alternatives Program)

PROJECT STATUS

The project is complete.

CONTACT

Joe Temple, Project Manager
(970) 498-5717
Email Joe Temple

Resurfacing of Red Mountain Road (CR 37)

With Improvements at the Switchbacks and Snow Drifting Areas

Project No. 6015

(CR 37 Improvements)

(CR 37 Permanent Roadway Flood Repairs)

Last Updated: September, 2018

 

SCOPE OF WORK

The County Road & Bridge Department will place an 8” thickness of gravel road base (treated with a dust suppressant) on Red Mountain Road (County Road 37) from Highway 287 to the state line - to an approximate 26’ width.  At locations where drifting snow has been a persistent problem the road profile may be raised and/or snow collection side ditches may be excavated.  Higher ground adjacent to the roadway outside the fence lines may be lowered where temporary construction easements are granted by the property owners.

Realignment of the road to improve the horizontal alignment at the switchbacks immediately south of the crossing of the South Branch of Boxelder Creek will be considered.  A preliminary design and cost estimate will be done to determine the feasibility of the improvements at this time.

Project Budget:  $589,000 ($464,000 ABC, $40,000 ROW, $50,000 Seeding, $35,000 Traffic Control) 

PROJECT STATUS

The project has been flown - processing of Lidar data has begun.  Ground survey work has begun.

A project open house will be held after a preliminary design is complete.

Construction by County Road & Bridge forces will be done in 2019.

CONTACT

Joe Temple
(970) 498-57217
Email Joe Temple

Crown Point Drive Bridge Replacement

Project No. 8085

(Replacement of Bridge No. LRCROWNPTDR1 over the Cache la Poudre River)

Last Updated: September, 2018

 

SCOPE OF WORK

The project includes the replacement of this deteriorating wood bridge on Crown Point Drive over the Cache la Poudre west of Rustic and just south of State Highway 14.  Stantec was selected as the design consultant.  Construction is currently scheduled for February through April of 2018.  This project is funded through a local improvement district with the property owners.

Project Budget:  $800,000

PROJECT STATUS

The bridge is complete and opened to traffic.

CONTACT:

Morgan Fay, Project Manager
970) 498-5739
Email Morgan Fay

County Road 15 Bridge Replacement

Project No. 9310

(Replacement of Bridge No. LR15-0.9-4 over the Little Thompson River)

Last Updated: September, 2018

 

SCOPE OF WORK

The project includes the replacement of this deteriorating concrete bridge on County Road 15 over the Little Thompson River south of Berthoud. Approximately 500 feet of roadway north and 800 south of the 146 foot long new bridge (1446 feet total) will be reconstructed with the project. AECOM was selected as the design consultant. Construction is scheduled from mid-January into July of 2018. This project is funded through a Federal Highway Administration flood recovery grant.

Project Budget: $2,400,000

PROJECT STATUS

Bridge and roadway work is complete and the road was opened to traffic on June 9th.

CONTACT

Morgan Fay, Project Manager
(970) 498-5739
Email Morgan Fay

Buckhorn Road West of CR 27 to be Improved

Project No. 9330

County Road 44H (Buckhorn Road) Flood Repair

Last Updated: September, 2018

 

SCOPE OF WORK

The County was on track to advertise the project for bids last spring after a full Environmental Assessment but FEMA defunded the greater reconstruction project and will fund only improvements to bring the road back to pre-flood conditions plus some undetermined mitigation work.    

Construction Budget:  $TBD 

PROJECT STATUS

Revised plans and mitigation proposals have been submitted to FEMA.  It’s hoped construction will take place in 2019.

CONTACT

Joe Temple, Project Manager
(970) 498-5717
Email Joe Temple

Big Elk Meadows Road (CR 47) to be Reconstructed

Project No. 9332

(CR 47 Permanent Roadway Flood Repairs)

Last Updated: September, 2018

 

SCOPE OF WORK

The remaining work consists of rebuilding and paving 2 miles of CR 47 including three crossings of the West Fork of the Little Thompson River in lieu of damages caused during September 2013 Flooding.  The goal is to make the repaired sections and crossings more resilient during future high flow events.

Reconstruction/realignment work on County Road 47 from Highway 36 South approximately 900' began in mid-2015.  This portion was managed through a contract with the Federal Highway Administration, Central Federal Lands Highway Division (CFL). Traffic was diverted over the new bridge during the summer of 2015.  Larimer County contracted the paving of the first 900’ and guardrail placement at the new bridge.  This work is complete.

PROJECT STATUS

Aerial surveying of CR 47 was conducted during the Fall of 2014.  Larimer County also hired an engineering consulting firm, Interwest, in 2014 to design and prepare construction plans.  The preliminary design package was submitted to state and federal agencies in May 2017 for review.

Further design of the three permanent creek crossings and roadway improvements has been suspended pending an appeal of FEMA’s Spring 2018 funding determination and a second scope change request for additional funds.  Larimer County is still in the process of determining what type of repairs and funding will be eligible for reimbursement from FEMA and State agencies.

Construction timelines can be better estimated once final plans have been submitted, reviewed, and approved by state and federal agencies.  However, construction is not anticipated to begin in 2018.

Project Budget: Larimer County is seeking federal (FEMA – 75%) and state (Office of Emergency Management and a HUD Community Block Grant – each 12.5%) reimbursement for the proposed repairs.  Preliminary Project Cost Estimate = $7,500,000; FEMA’s recent funding determination only allows approximately $3,000,000.  Larimer County submitted the second scope change request in May 2018 for approximately $6,300,000 which is still under review by FEMA.

CONTACT

Matt Johnson, Project Manager
(970) 498-5724
Email Matt Johnson