INTERSECTION IMPROVEMENTS PLANNED
FOR TWO INTERSECTIONS ON COUNTY ROAD 30

Project Number 306
(CR 30/CR 11 & CR 30/CR 11C Intersections North of Loveland)

Last Updated: January 16,2015

SCOPE OF WORK

Improvements to two intersections (CR 30/CR 11 & CR 30/CR 11C). The improvements include construction of modern roundabouts at each intersection.

Project Budget: $1,000,000

PROJECT STATUS

The project is complete and all roadways are open. Landscaping is scheduled to be installed in the spring of 2015.

CONTACT

Kyle Arend, Project Manager
(970) 498-5734
Send e-mail