Technical staff from local governmental entities, as well as other interested parties, begin addressing the stormwater needs in the Boxelder Creek Watershed.
Master Plan Study is completed (both engineering and public process components) and adopted
Larimer County successfully applied for FEMA Pre-Disaster Mitigation Grant that will help fund first portion of the regional project (Clark Reservoir expansion).
Stormwater Authority proposed and approved through Intergovernmental Agreement by Fort Collins, Wellington, and Larimer County as mechanism to manage regional projects.
Ongoing public outreach has included newsletters, meetings, field visits, and open houses.
Public outreach continues as funding and project details become available.
Execution of the approved Inter-governmental Agreement to create the Stormwater Authority.
Continued public outreach and dialogue for general Stormwater Authority, local proposed Stormwater Utility and related fees.
Mark your Calendars! A drop-in Open House will be held on October 1, 2, and 3 at the Larimer County Engineering Department, 200 W. Oak St, Suite 3000 (3rd Floor). Drop by anytime between 1:00 pm and 5:00 pm with extended hours to 6:30 pm on October 2nd.
Public Hearing for Board of County Commissioner consideration of stormwater utility and fees. This is tentatively scheduled for November, 2008.
Begin Clark Reservoir expansion project (design and public outreach)